U.S. 20 Bend Facility Plan 3rd Street to Powell Butte Highway

Planning Phase

Region 4: Central Oregon (Bend, Deschutes)


​​​​ODOT is preparing the U.S. 20 Bend Facility Plan to evaluate how the highway operates and what measures are needed to keep it functioning well in the future.​


https://www-auth.oregon.gov/odot/Projects/Project%20Images/DesignBanner.jpg

Impacts

Schedule

​The planning process started in fall 2022 and the final plan is due fall 2023. See below for the full project schedule. 

U.S. 20 Bend Facility Plan Schedule.PNG


Details

About

​ODOT is planning improvements to help people get around U.S. 20 more safely now and in the future. The U.S. 20 Bend Facility Plan begins at the intersection of 3rd Street and Greenwood Avenue and ends at the intersection of Powell Butte Highway.

This Project will assess existing and future conditions and identify strategies to improve safety, mobility and reliability for all modes of travel.

The plan aims to:

  • Improve efficiency, reliability, and connectivity for all users
  • Ensure safety access for all users
  • Support economic development and livability
  •  and ensure equity and access
  • Protect the environment
  • Develop cost-effective and feasible solutions

U.S. 20 is a heavily used highway in central Oregon, serving the residents of Bend, freight, and other travelers. As the region grows, so have congestion and safety concerns.

The U.S. 20 Bend Facility Plan will identify strategies to improve safety for all users, with an emphasis on improvements for people who walk, bike and use public transit.

The study area  begins at the intersection of 3rd Street and Greenwood Avenue, continuing east to the intersection of Powell Butte Highway near Mile Point 4.8.


We are developing this plan in close coordination with state and local jurisdictions, including Deschutes County, the City of Bend, community organizations and highway users.

Location

U.S. 20 |

3rd Street to Powell Butte Highway.

Cost and Funding

​The current estimate for the project is $350,000.

Contacts & Media

Project Contacts

Senior Transporation Planner
Don Morehouse
Email
donald.morehouse@odot.oregon.gov
Phone
541-388-6046

Community Affairs
Meghan Blyth
Email
meghan.l.blyth@odot.oregon.gov
Phone
541-316-3941

Last Updated

3/25/2024 2:15 PM

Project Number

00006

Project Documents

Related documents to this project
U.S. 20 Technical Memo 1 - Plans and Policy Review.pdfU.S. 20 Technical Memo 1 - Plans and Policy Review
U.S. 20 Technical Memo 2 - Existing Transportation System Conditions.pdfU.S. 20 Technical Memo 2 - Existing Transportation System Conditions
U.S. 20 Technical Memo 3 - Future Traffic Forecast.pdfU.S. 20 Technical Memo 3 - Future Traffic Forecast
U.S. 20 Technical Memo 4 - Future Baseline (No-Build) Transportation System Conditions.pdfU.S. 20 Technical Memo 4 - Future Baseline (No-Build) Transportation System Conditions
U.S. 20 Technical Memo 5 - Alternatives.pdfU.S. 20 Technical Memo 5 - Alternatives
U.S. 20 Technical Memo 6 - First Level Screening.pdfU.S. 20 Technical Memo 6 - First Level Screening